Urd is producing 1,970 barrels of oil equivalent a day — 0.1% of everything the Norwegian Continental Shelf produced in May 2026, ranking 82 of the 94 fields in production.

Production
1,970 boe/d
Share of NCS
0.1%
Operator
Equinor Energy AS
First oil
2005

What it produces

In May 2026 the field delivered 1,970 barrels of oil equivalent a day, classified by the directorate as oil — almost entirely oil. Output has moved down 5.1% over the past twelve months, and the directorate's profile for the field is late life. The field's best year was 2006, averaging 36,741 boe/d — today it runs at 5% of that.

Since 2005, Urd has produced roughly 54 million barrels of oil equivalent in total. The directorate's estimate of recoverable resources is 60 million boe, of which about 90% has now been recovered; 6 million boe remained as of 31.12.2025.

Timeline

  1. 2000
    Proven by exploration well 6608/10-6
  2. 2005
    First production reported
  3. 2006
    Best year to date — 36,741 boe/d

Production by year, 2005–2026

2006 · 36,74120052026
OilGasNGL/condensateboe/d
Full table, year by year
YearOilGasNGLTotal boe/d
20053,294196453,534
200635,2361,19131436,741
200714,58154614415,270
20088,772355969,223
20096,261112316,404
20107,13650147,200
20115,4152885,450
20125,58039115,630
20134,7075461225,374
20146,6781,1142538,045
20154,422291534,767
20164,474338574,870
20178,921139109,071
20184,736004,736
20193,184003,184
20202,175002,175
20213,109003,109
20224,127004,127
20231,960001,960
20243,186003,186
20252,157112,159
20262,8081552,828

Average daily rates per calendar year, from Sokkeldirektoratet's monthly production figures. The final year is the average through May 2026.

Discovery and drilling

The field was proven by exploration well 6608/10-6 in 2000. The directorate's wellbore register lists 30 wellbores on Urd: 9 exploration and 21 development. The deepest reaches 3,981 metres measured depth. Water depth at the field's installations is 390 metres.

Installations on Urd

    The field also has 3 subsea structures — wellheads and templates on the seabed — which are drawn individually on the map.

    Licence partners

    • Equinor Energy AS63.95%
    • Petoro AS24.55%
    • DNO Norge AS11.50%

    The field sits in block 6608/10, under production licence PL 128.

    Questions people ask

    Who operates the Urd field?
    Urd is operated by Equinor Energy AS, in partnership with Petoro AS, DNO Norge AS.
    How much does Urd produce?
    1,970 barrels of oil equivalent per day as of May 2026 — 0.1% of Norwegian Continental Shelf output, ranking 82 of 94 producing fields.
    When did Urd start producing?
    First production was reported in 2005, 5 years after discovery well 6608/10-6 proved the field in 2000.

    See it live

    Urd is drawn on the NCS Live map with its outline, its pipelines and the vessels working it in real time — and på norsk. The directorate's own record is on the SODIR FactPages.

    Other fields in the Norwegian sea

    Ormen LangeÅsgardSkarvAasta HansteenHalten ØstHeidrunTyrihansNjordAll fields →